A commercial vehicle manufacturer in Shandong Province built a new production line for new-energy logistics vehicles two years ago. Before launching the new models, it needed to conduct rain‑proof sealing tests, so the company decided to construct its own full‑vehicle rain test chamber. The procurement department compared quotes from three suppliers and selected the one with the lowest price. From contract signing to delivery, the project took four months; on the day the rain test chamber was completed, the vice president of manufacturing attended the ribbon‑cutting ceremony on site.

In its first month of operation, the full‑vehicle rain test chamber began to experience problems. First, the variable‑frequency pump in the spray system triggered frequent alarms and shut down; after three service visits, each time the issue was resolved by simply replacing a capacitor, but it failed again within two weeks. In the second month, insufficient slope in the drainage trench at the base of the chamber caused water to pool, requiring manual removal after each test; otherwise, water would overflow into the workshop aisle. By the third month, the problems came to a head: multiple welds in the spray piping had corroded through, and as soon as water pressure increased, leaks sprayed everywhere, turning the entire rain test chamber into a scene resembling a torrential downpour.

 Rain Test Chamber

When Sun, the head of the Quality Control Department, arrived on site after receiving a call that morning, the sprinkler system in the vehicle full‑vehicle rain‑test chamber had already completely shut down. The floor was awash with water, and several logistics vehicles that had just finished testing were still parked on the turntable, their door gaps soaked with water. Sun called the supplier’s after‑sales service; they replied, “The parts need to be sourced from another province and will take five days.” After hanging up, Sun let out a curse— he knew all too well how much a five‑day production halt would cost.

What gave Engineer Sun even more headaches was something else. In the month before the vehicle full‑vehicle rain‑test chamber was shut down, they had conducted rain tests on over two hundred vehicles, and all of them had passed. But a few days ago, he randomly selected three of those “qualified” cars for a retest using manual spray nozzles—and water leaked in at the window seal on two of them. What did this mean? It meant that the spray coverage in that full‑vehicle rain‑test chamber was fundamentally inadequate; at certain points along the vehicle’s sides, the water pressure was insufficient, making it impossible to detect the leak points. Those “qualified” results were all false.

After Engineer Sun reported the situation, the company decided to dismantle the vehicle full‑vehicle rain‑test chamber, which had been in use for less than six months, and reissue the tender. For this round of bidding, Engineer Sun personally drafted the technical specifications, detailing everything from the spray system’s material and drainage slope to water pressure uniformity and pipe‑welding procedures. Among the three shortlisted suppliers, he chose Guangzhou Yuexin. He later told his peers that the reason was simple: other vendors came to the site to discuss price and schedule, but only Yuexin’s team used a ruler to measure slopes on the ground, a level to check floor flatness, and an electrical panel to assess incoming line capacity.

Complete vehicles manufactured by Guangzhou Yuexin Rain Test Chamber The structure features a stainless steel frame with tempered glass. All piping is welded from 304 stainless steel, and the welds undergo pickling and passivation for ten-year corrosion resistance. The drainage channel is designed with a 0.5% slope, and the drainage pump capacity is sized at 1.5 times the maximum spray flow rate; testing confirms complete drainage within thirty seconds. The spray system strictly complies with GB/T 4208 national standards, enabling stable switching among multiple operating modes from IPX3 to IPX6. Nozzle placement was optimized through fluid dynamics simulation, ensuring water pressure variation across all vehicle body areas remains below 8%.

One aspect that Engineer Sun is particularly pleased with is the control system—housed in an outdoor control cabinet. It features a touchscreen interface: after setting the spray duration, water pressure, and turntable speed, a single button starts the operation, and data is automatically recorded for traceability. After each test, the system generates a report detailing which vehicle was tested, when, how long it was sprayed, and the water pressure—all readily accessible.

New complete vehicles Rain Test Chamber I’ve been using it for over a year, and it hasn’t had a single malfunction. Engineer Sun says that when choosing a full‑vehicle rain‑test chamber, the small price difference isn’t worth it. A reliable chamber can save you enough in production downtime and after‑sales costs to pay for itself within a year.

 

© 2023  Guangzhou Yuexin Testing Equipment Co., Ltd   All rights reserved.   SEO   Website: WWW.300.CN   business license

Tel:400-997-0881

No.3 Jiangjunzi, Jiangxi Village, Dalong Street Office, Shiqi Town, Panyu District, Guangzhou City

E-mail:yxipx@yxipx.com

We will provide you with timely feedback